Lump sum contract - pros and cons
A lump sum contract is the traditional means of procuring construction, and involves a single ‘lump sum’ price for all the works being agreed before the works begin.
It is generally considered a beneficial contract agreement if the work is well defined when tenders are sought and significant changes to requirements are unlikely. This means that the contractor is able to accurately price the works they are being asked to carry out.
The advantages of a lump sum contract include:
- Lump sum contracts can be seen to reduce client risk as the price is fixed (although in reality it is still likely to vary, but not by as much as some other forms of contracting).
- It is widely accepted and understood as a method of contracting.
- The bidding analysis and selection process is relatively straight-forward.
- The greater degree of certainty on the part of the client can make it simpler and easier to secure a construction loan.
- Change orders are minimised.
- The management required by the client is reduced.
- There can under certain circumstances be a greater margin for profit for the contractor.
- Lump sum payments are made in regular, predictable instalments, providing the contractor with a reliable and stable cash flow and making financing simpler for the client.
Disadvantages include:
- It can give greater risk to the contractor than some other contract forms, as there are fewer mechanisms available for them to vary their price.
- As a result of the additional risks faced by the contractor, they may increase their tender price.
- Careful documentation and record keeping of change orders is required, which can be time-intensive.
- Preparing the tender may be more expensive for the contractor.
- As a result, there may be a slower tender process than for other contract forms.
- Progress may be slower as the design will generally need to be completed before the works begin.
- The employer may have to pay a higher price for any alteration or additions that are required that are beyond the scope of the contract.
- It can be seen as a more adversarial form of contracting than some more collaborative forms.
- Disputes can arise relating to change orders, scope and design changes, and so on.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.
The story of this knowledge quarter building.
In ecology, in hydrology, in biology and in architecture.
Creating environments that promote physical, mental, and social well-being.
UK cases of neutral current diversion
Research project looks for example contributions.
Overstocking and macro-economics cause a decline.
The 2024 update of the Common Assessment Standard
Demonstrating organisational capability’ to fulfil roles under the Building Safety Act.
56 recommendations for a better built environment
Published by the CIC ahead of the King’s Speech.
SkillELECTRIC Top 8 Competitors Named
in annual search for the UK’s best student electrician.
CIOB Diversity and Inclusion technical information sheet
Step-by-step guide on implementing D and I practices.
Conservation and the Indian City. Book review.
Reversibility in conservation ethics
Learning from painting conservation.
Where It's AT Podcast launched!
New CIAT Architectural Technology Podcast goes live.