Lump sum contract - pros and cons
A lump sum contract is the traditional means of procuring construction, and involves a single ‘lump sum’ price for all the works being agreed before the works begin.
It is generally considered a beneficial contract agreement if the work is well defined when tenders are sought and significant changes to requirements are unlikely. This means that the contractor is able to accurately price the works they are being asked to carry out.
The advantages of a lump sum contract include:
- Lump sum contracts can be seen to reduce client risk as the price is fixed (although in reality it is still likely to vary, but not by as much as some other forms of contracting).
- It is widely accepted and understood as a method of contracting.
- The bidding analysis and selection process is relatively straight-forward.
- The greater degree of certainty on the part of the client can make it simpler and easier to secure a construction loan.
- Change orders are minimised.
- The management required by the client is reduced.
- There can under certain circumstances be a greater margin for profit for the contractor.
- Lump sum payments are made in regular, predictable instalments, providing the contractor with a reliable and stable cash flow and making financing simpler for the client.
Disadvantages include:
- It can give greater risk to the contractor than some other contract forms, as there are fewer mechanisms available for them to vary their price.
- As a result of the additional risks faced by the contractor, they may increase their tender price.
- Careful documentation and record keeping of change orders is required, which can be time-intensive.
- Preparing the tender may be more expensive for the contractor.
- As a result, there may be a slower tender process than for other contract forms.
- Progress may be slower as the design will generally need to be completed before the works begin.
- The employer may have to pay a higher price for any alteration or additions that are required that are beyond the scope of the contract.
- It can be seen as a more adversarial form of contracting than some more collaborative forms.
- Disputes can arise relating to change orders, scope and design changes, and so on.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February